Case Study

12×9m Office Complex

Alpha HPA • Yarwun, Central QLD

Resources / Refining • Turnkey Delivery • Ahead of Schedule

12×9m
Office Complex
Ahead
Of Schedule
Custom
Engineering
Hire
Flexible Terms
12×9m office complex at Alpha HPA Yarwun — front elevation with dual entry ramps
About the Client

Alpha HPA — Pioneering High-Purity Alumina

Alpha HPA is an Australian company that has commercialised a purification technique for aluminium, producing a range of ultra-high purity aluminium materials. Following the success of their Stage 1 facility at Yarwun, Alpha HPA is constructing a larger scale facility set to become one of the largest single-site ultra-high-purity alumina refineries globally.

The Challenge

Limited Space, Complex Foundations

As Alpha HPA scaled toward Stage 2 commissioning, the site needed dedicated office space for a growing Operational Readiness team. Available space at the Yarwun facility was extremely limited.

The solution required creative site planning: the office complex would need to be constructed over an existing swale drain to conserve room on site. This introduced engineering complexity around foundations and structural support that went well beyond a standard modular building deployment.

Office complex exterior — angle view with entry ramps

Exterior — showing raised foundations and dual access ramps with safety railings

Office complex rear three-quarter view

Three-quarter view — full complex with air conditioning and entry ramps at both ends

The Solution

Custom Engineering, Turnkey Delivery

Multitrade Building Hire worked closely with Alpha HPA to design and deliver a fit-for-purpose 12×9m office complex tailored to the site's constraints. After the installation location was confirmed, the MBH team arranged for engineering to visit site and address all requirements for building over the swale drain.

Steel beams were fabricated and welded to custom footings to support the structure. Multitrade coordinated the full scope of work, including transportation of beams, crane hire for lifting into position, and a boilermaker to weld beams to footings on site. All excavation and electrical works were completed in full compliance with the site's permitting requirements.

The installation ran smoothly and was completed ahead of schedule, allowing Alpha HPA to hand over the space to their operations team on time.

Project Snapshot

At a Glance

Client
Alpha HPA
Location
Yarwun, Central QLD
Building
12m × 9m Office Complex
Sector
Resources / Refining
Contract Type
Hire — flexible terms with ability to extend or adjust
Delivery Model
Full turnkey — site assessment, custom engineering, transport, crane hire, installation
Scope of Works
Engineering site visit, custom steel beam fabrication, welded footings over swale drain, crane lift, boilermaker on site, transportation of beams, full installation, electrical works — all under site permitting requirements
Key Features
Open-plan office layout with workstation partitions, multiple entry points with DDA-compliant ramps and yellow safety railings, split-system air conditioning, windows with security screens
Project
Alpha HPA Stage 2 — Operational Readiness Team office space
How We Delivered It

End-to-End Project Management

Multitrade handled every phase — from engineering assessment to ahead-of-schedule handover:

01

Site Assessment & Engineering

After the installation location was confirmed, the Multitrade team arranged for engineering to visit site and assess all requirements for building over the existing swale drain.

02

Custom Foundation Design

Steel beams were fabricated and welded to custom footings designed to span the swale drain — a solution that preserved the drainage infrastructure while providing a stable foundation for the complex.

03

Transport & Logistics

Multitrade coordinated transportation of the office complex modules and steel beams to the Yarwun site, managing all logistics for the restricted-access refinery environment.

04

Crane Lift & Placement

Crane hire was arranged to lift the steel beams and building modules into position. A boilermaker attended site to weld beams to footings, ensuring structural integrity.

05

Services & Compliance

All excavation and electrical works were completed in full compliance with the site’s permitting requirements, meeting the stringent safety standards of the Alpha HPA facility.

06

Handover — Ahead of Schedule

The installation ran smoothly and was completed ahead of schedule, allowing Alpha HPA to hand over the space to their Operational Readiness team on time for Stage 2 preparations.

The Outcome

Fit for Purpose, Ready to Scale

The office complex has proven fit for purpose as the Operational Readiness team continues to grow in preparation for Alpha HPA's Stage 2 project. The hire arrangement has provided the flexibility needed to scale up as required, with the ability to extend or adjust agreements without issue.

Interior — open-plan office with workstation partitions

Interior — open-plan office layout with workstation partitions, ready for the operations team

Side view showing building on custom steel foundations

Side elevation — building raised on custom steel beam foundations over the swale drain

From start to finish, the team at Multitrade demonstrated exceptional professionalism and support. They were consistently easy to work with, responsive, and committed to delivering a high-quality product on time.

Marion Gluestein
General Superintendent, Alpha HPA
Gallery

The Finished Product

Corner view showing AC units, yellow safety ramp, and custom steel beam foundations
Front elevation with windows, dual entry ramps and yellow safety railings
Rear three-quarter view showing the full complex with entry ramps at both ends
Interior — open-plan office with blue workstation partitions and desks
Exterior angle view with Multitrade signage, ramp and steel beam foundations
12×9m office complex — exterior view at Alpha HPA Yarwun
Office complex exterior — Alpha HPA Yarwun facility
Office complex — Alpha HPA Yarwun site
Why Multitrade

Why Alpha HPA Chose Multitrade

Turnkey delivery, one point of contact

From engineering site visits to crane hire and boilermaker coordination — Multitrade managed the full scope so Alpha HPA didn’t have to.

Custom engineering for complex sites

When the install location included a swale drain, we designed and fabricated custom steel beam foundations to solve the problem without compromise.

Delivered ahead of schedule

The installation was completed ahead of the agreed timeline, giving the client’s Operational Readiness team early access to their workspace.

Flexible hire arrangements

The hire model gives Alpha HPA the flexibility to scale up, extend agreements, or adjust as their Stage 2 project evolves — without capital commitment.

Planning a Similar Project?

Talk to Multitrade Building Hire about your office complex, site accommodation, or modular building needs.

Call NowGet a Quote